October’s anticipated start
On 14 October 2024, Liam Brett told councillors that Phase 1 would begin in November.

2
00:00:10,000 --> 00:00:20,000
Signs in preparation
The October minutes also record that signs were being centrally procured and delivery was expected shortly.

3
00:00:20,000 --> 00:00:30,000
January’s stated date
By the January 2025 meeting, the recorded implementation date for the rural-local-road change was 7 February.

4
00:00:30,000 --> 00:00:40,000
The confirmed implementation
The Department’s 7 February 2025 release confirms the rural-local default changed from 80 to 60 km/h that day.

5
00:00:40,000 --> 00:00:50,000
The dates do not explain the reason
The October plan and February implementation differ. This sequence alone does not establish why the timetable changed.

6
00:00:50,000 --> 00:01:00,000
Locate the revised instruction
Which dated instruction records the move from the anticipated November start to February implementation?

7
00:01:00,000 --> 00:01:10,000
Bronagh English — The Record
Factual record. No finding of causation or responsibility is made here.